WORKED DEFAULT
Check the calculation with the default inputs
If 184 of 200 production orders due under the frozen plan are complete by the cutoff, schedule attainment is 92.00%.
- Freeze the denominatorScheduled orders due
- Apply one numerator ruleScheduled orders completed by cutoff
- Calculate and interpretSchedule attainment = scheduled orders completed by cutoff / scheduled orders due x 100%.