WORKED DEFAULT
Check the calculation with the default inputs
If 184 of 200 released planned work orders pass every required planning checkpoint, planning completeness is 92.00%.
- Freeze the denominatorReleased planned orders assessed
- Apply one numerator ruleReleased orders passing planning checklist
- Calculate and interpretPlanning completeness = orders passing every check / released planned orders assessed x 100%.